Knowledge

20 types of daily maintenance methods for mechanical equipment, worth collecting

01 Regular lathe daily maintenance
Before starting work:
1. Clean the dust on the exposed guide rail surface and sliding surface of the machine tool and add oil;
2. Lubricating all parts according to regulations;
3. Check the position of each handle;
4. Empty vehicle test run.
During the work process:
1. Strictly follow the operating procedures;
2. Pay attention to the operation of the machine tool at all times and promptly handle any abnormalities.
After work is completed:
1. Clean up all the iron filings;
2. Clean all parts of the machine tool;
3. Component positioning.
Weekend:
1. Thoroughly wipe all parts of the machine tool to keep the paint visible and the iron visible;
2. Check if the fasteners are loose;
3. Check and clean the yarn and felt;
4. Lubricating all components.
02 Daily Maintenance of CNC Lathe
1. Clean and lubricate each guide rail surface every day. Machine tools with automatic lubrication systems should regularly check and clean the automatic lubrication system, check the oil level, add lubricating oil in a timely manner, and check whether the oil pump starts and stops regularly;
2. Check whether the automatic lubrication system of the spindle box is working properly every day, and replace the lubricating oil of the spindle box regularly;
3. Pay attention to checking whether the cooling fan in the electrical cabinet is working properly, whether the air duct filter screen is blocked, and clean any dust adhering to it;
4. Pay attention to checking the cooling system, check the liquid level, and add oil or water in a timely manner. If the oil or water is dirty, it should be replaced and cleaned;
5. Pay attention to checking the spindle drive belt and adjusting the tightness;
6. Pay attention to checking the tightness of the guide rail insert and adjusting the gap;
7. Pay attention to checking whether there is any abnormal noise in the oil tank and pump of the machine tool hydraulic system, whether the working oil level is appropriate, whether the pressure gauge indicates normally, and whether there is any leakage in the pipelines and joints;
8. Pay attention to checking whether the guide rails and machine tool protective covers are complete and effective;
9. Pay attention to checking the mechanical accuracy of each moving component to reduce shape and position deviations;
10. After work every day, do a good job of cleaning and cleaning the machine tool, removing iron filings, and wiping the cooling liquid on the guide rail to prevent rust on the guide rail.
03 Daily Maintenance of Vertical Lathe
Daily maintenance content and requirements:
Time: 10 minutes before and after taking over every day, and 1 hour on weekends;
Responsible person: The operator performs the inspection, and the inspector inspects it.
Before starting work:
Check the handover notebook;
Strictly follow the lubrication chart of the equipment for refueling, ensuring timely, quantitative, and quality control;
For equipment that has been shut down for more than 8 hours, when not starting the equipment, it is necessary to first slow down for 3-5 minutes to confirm whether the lubrication system is smooth and whether all parts are running normally before starting work.
During the work process:
A. Regularly check the operation of various parts of the equipment and the working condition of the lubrication system. If there are any abnormal situations, immediately notify the inspection personnel to handle them;
B. Tools, workpieces, metal objects, and foot pedals are strictly prohibited from being placed on each guide rail surface and protective cover.
After work is completed:
A. Wipe off the iron filings and coolant on the guide rail surface, and ensure that there is no black oil on the screw and polished rod;
B. Clean up iron filings and debris around the equipment;
C. Fill in the equipment handover record truthfully.
04 Daily maintenance of medium frequency induction furnace
1. Thoroughly remove the oxide residue in the sensing body. Carefully inspect the insulation furnace lining for any damage or cracks, and promptly address any issues found;
2. Check the waterway to ensure that it is unobstructed, with sufficient return water and no leakage. The inlet water temperature should not exceed 35 ° C;
3. Observe whether the varistor, protective resistor, and capacitor appearance inside the intermediate frequency power cabinet are normal, whether the fastening bolts are loose, whether the solder joints are detached, and whether there is any leakage of the capacitor electrolyte. Promptly notify maintenance personnel of any issues discovered;
4. The equipped hoist needs to be lubricated regularly.
05 Boring Machine Daily Maintenance
Before starting work:
Check whether the various components and mechanisms of the machine tool are intact, and whether the positions of each handle are normal; Clean all parts of the machine tool, observe each lubrication device, directly lubricate the guide surface of the machine tool with oil, and start the machine at low speed and idle for a certain period of time.
During the work process:
Mainly for correct operation, the machine tool is not allowed to work under overload, and precision machine tools cannot be used for rough machining, etc. If any abnormal phenomena are found during the work process, the machine should be stopped immediately for inspection.
After work is completed:
Clean all parts of the machine tool, move the moving parts to the designated positions, and turn off the power.
06 Routine maintenance of centerless grinding machine
1. The main spindle oil pressure is limited to 8-10kg/cm;
2. Before starting the machine, use an oil injector to lubricate the machine tool appropriately;
3. Repair the seat skateboard by adding an appropriate amount of lubricating oil every day and keeping the skateboard clean (clean, free of debris, impurities, and in a lubricated state);
4. Regularly check the tightness of the zipper;
5. Regularly check the tightness of the grinding wheel drive belt;
6. Replace the spindle of the machine tool every 2000 hours of use.
07 Daily maintenance of cylindrical grinding machine
1. After completing homework every day, use a brush to clean the entire body of the external circular grinder. It is strictly prohibited to use an air gun to blow directly on the worktable or guide rail to prevent iron filings from entering the guide rail and affecting the accuracy of the cylindrical grinder;
2. It is strictly prohibited to use a fan to blow towards the workbench during homework to prevent dust and iron filings from rolling back into the guide rail, affecting the accuracy and feel of the guide rail;
3. The guide rail oil of the cylindrical grinder should be replaced and added in a timely manner. Generally, if the oil in the oil mirror is cloudy or black, it should be replaced. The time should be controlled to replace it every 3-6 months, the first three months, and the next six months;
4. Please use professional lubricating oil for the guide rail of the cylindrical grinder, generally 32 # guide rail oil is recommended;
5. Regularly check whether the steel cables of the outer grinding machine workbench are loose, lock them to prevent breakage or affect the tactile accuracy;
6. Regularly clean the workbench guide rail to prevent iron filings from wearing the guide rail surface, which may affect the accuracy of the guide rail. For cleaning, use a gasoline cloth to wipe it clean. For debris embedded with wear-resistant plates, gently remove them with a shovel. The above actions should be carried out under the guidance of professionals or handled by the master of the external grinding machine manufacturer;
7. Regularly check whether the body of the cylindrical grinder is unstable and level during operation;
8. If it is a manual cylindrical grinder, the tightness of the steel cable should be checked regularly;
If it is a semi-automatic cylindrical grinder, the grinding fluid concentration should be checked weekly and replaced in a timely manner.
08 Daily maintenance of punching machine
1. According to lubrication requirements, inject lubricating oil into the oil holes and sliding parts;
2. Strictly comply with the safety operation requirements of the punching machine;
3. Before use, the equipment should be idle for 3 minutes and observed for any abnormalities;
4. When installing the mold, the power should be cut off;
5. After completing work, the workbench should be wiped clean, and any scraps or debris should be removed. The power should be cut off;
6. Clean the workplace.
09 Daily maintenance of milling machine
Before starting work:
1. Inspect important parts;
2. Clean the exposed guide rail surface and lubricate all parts according to regulations;
3. Run it by air and check if the lubrication system is functioning properly. Check each oil level, not lower than the oil mark, and add lubricating oil to each part.
After work is completed:
1. Do a good job in cleaning the bed and its components, clean iron filings and maintain hygiene in the surrounding environment;
2. Wipe the machine tool;
3. Cleaners, clamps, and measuring tools;
4. Each department should return to their original position.
10. Daily maintenance of drilling machine
Before starting work:
1. Clean the dust on the exposed guide rail surface and worktable surface;
2. According to regulations, lubricate each part with oil that meets the requirements;
3. Check the flexibility and reliability of each handle;
4. Empty vehicle test run.
After work is completed:
1. Clean up all the iron filings;
2. Clean all parts of the machine tool;
3. Component positioning.
11. Daily maintenance of hydraulic press
1. L-HL32/GB118-89 hydraulic oil. When it is below 20 degrees, N32/GB3141 can be used. When it is above 30 degrees, N46/GB3141 can be used. It is recommended to use No. 32 and No. 46 anti-wear hydraulic oil for work, with an oil temperature of 15-60 degrees Celsius;
2. The oil industry must undergo strict filtration before it can be added to the fuel tank;
3. The working oil should be replaced once a year, and the first replacement should not exceed three months;
4. The slider should be lubricated regularly, and the exposed surface of the column should be kept clean regularly. Before each operation, oil should be sprayed first;
5. Under a nominal pressure of 500T, the maximum allowable eccentricity of the concentrated load is 40mm. Excessive eccentricity can easily cause damage or other adverse phenomena to the column;
6. Calibrate and inspect the pressure gauge every six months;
7. If the machine is not used for a long time, the surfaces of each processing plant should be cleaned and coated with anti rust oil;
8. At the end of each day's work: Place the slider to the lowest position.
Daily maintenance of 12 milling and drilling machines
Before starting the machine, check whether each clamping mechanism is clamped, whether the lifting and movement of the spindle sleeve and the electrical equipment are normal, and whether the grounding wire is reliably grounded (yellow green dual color wire is the grounding wire);
2. If there is a power outage during work, the power switch should be immediately cut off to avoid adverse consequences during operation or when the machine tool automatically starts;
After completing the work, iron shavings and dirt should be removed from the machine, and anti rust oil should be applied to the unpainted surface to prevent rusting.
13. Daily maintenance of air storage tanks
1. Check if the safety valve is functioning properly;
2. Check the condition and position of the pressure gauge. When there is no pressure, the position of the pressure gauge is in the "0" state, that is, at the limit pin;
3. Slowly open the exhaust valve to the appropriate opening to remove moisture from the tank;
4. First check the sealing of the pipeline to ensure that there are no abnormalities before opening the intake valve;
5. Observe the intake process, pipelines, and tank body for leaks until the operating pressure is reached;
6. Drain the gas storage tank at least twice per shift;
7. Check whether there are corrosive gases and fluids around the gas storage tank every day;
8. Check the indicated value of the pressure gauge every day. If any abnormal pressure phenomenon (i.e. malfunction) is found, replace it if it fails; The maximum working pressure should be<0.8MPa. If it is higher than 0.8MPa, the safety valve should automatically open. Otherwise, the intake should be stopped immediately and maintenance should be carried out;
9. Check the sealing of the air pressure pipeline, and if there is any leakage, it should be repaired in a timely manner.
14. Daily maintenance of ultrasonic cleaning machine
Daily maintenance: (after each operation)
1. Rinse the hoses and filters connected to the cleaning agent to remove any residue of the detergent to help prevent corrosion;
2. Turn off the water supply system connected to the high-pressure cleaning machine;
3. Pulling the trigger on the servo spray gun rod can release all the pressure in the hose;
4. Remove the rubber hose and high-pressure hose from the high-pressure cleaning machine;
5. Cut off the connecting wire of the spark plug to ensure that the engine will not start (applicable to engine models).
Daily maintenance of 15 pressure test press
1. The appearance of the equipment is clean and tidy;
2. The electrical and electronic control cabinet of the equipment is working normally;
3. The operation status of the equipment is normal, and the display signals of each indicator instrument are normal;
4. The adjustment operation handle and buttons of the equipment are flexible and reliable;
5. The safety protection device of the equipment is functioning properly;
6. The lubrication and cooling systems of the equipment are normal;
7. The surrounding area of the equipment should be clean, without any disorderly stacking of debris, and the temperature and humidity should be appropriate;
8. The auxiliary equipment of the main equipment is working normally and maintained to meet the requirements;
9. All types of operation and maintenance tools, instruments, appliances, spare parts and materials are neatly arranged.
16. Daily maintenance of fuel dispensers
1. The appearance of the equipment is clean and tidy;
2. The electrical and electronic control cabinet of the equipment is working normally;
3. The operation status of the equipment is normal, and the display signals of each indicator instrument are normal;
4. The adjustment operation handle and buttons of the equipment are flexible and reliable;
5. The safety protection device of the equipment is functioning properly;
6. The lubrication and cooling systems of the equipment are normal;
7. The surrounding area of the equipment should be clean, without any disorderly stacking of debris, and the temperature and humidity should be appropriate;
8. The auxiliary equipment of the main equipment is working normally and maintained to meet the requirements;
9. All types of operation and maintenance tools, instruments, appliances, spare parts and materials are neatly arranged.
Daily maintenance of the 17 arm drilling machine
1. Clean the surface and dead corners of the machine tool, remove and wash each cover, and ensure that the inside and outside are clean, free of rust, yellow robe, and the paint is visible in its natural color. Clean the guide rail surface and remove burrs from the workbench. Check and complete the screws, handball, and hand board, and check the flexibility and reliability of each handle;
2. Maintenance of the main spindle feed box of the radial drilling machine: Check the oil quality, keep it in good condition, and ensure that the oil level meets the requirements. Remove burrs from the spindle taper hole. Clean the hydraulic transmission system, oil filter, and adjust the oil pressure;
3. Inspection of the rocker arm and lifting clamping mechanism of the radial drilling machine: Check and adjust the lifting mechanism and clamping mechanism to ensure sensitivity and reliability;
4. Inspection of lubrication system for radial drilling machine: Clean the oil felt, ensure that the oil cup is complete, the oil circuit is unobstructed, and the oil window is bright;
5. Inspection of the cooling system of the radial drilling machine: Clean the cooling pump, filter, and coolant tank. Check the coolant pipeline and ensure that there is no water leakage;
6. Inspection of the electrical system of the rocker drilling machine: Clean the dust inside and outside the motor and electrical box. Turn off the power, open the electrical door cover, and check if the electrical connectors and components are loose or aging. Check if the limit switch is working properly. Does the power outage when opening the door work. Check if the hydraulic system is functioning properly and if there is any oil leakage. Are the control switches of each electrical appliance working properly.
Daily maintenance and upkeep of 18 gas shielded welding machines
1. Check for any looseness in the connection parts of the welding power supply; Internal inspection for dust and other debris;
2. Welding gun, nozzle cleaning, whether there is splashing adhesion, damage, deviation of the center of the conductive nozzle, whether there is wear on the conductive nozzle hole, whether there is looseness of the nozzle, damage to the trachea, blockage of the air hole, and whether there is blockage in the air screen and nozzle;
3. Check whether the cables are loose, damaged or decomposed, whether the wire feeding pipes are blocked, whether there are insulation problems, and whether the air screen and nozzle are damaged;
4. Wire feeding device. Whether the wire feeding wheel has been cleaned and whether the wire feeding wheel is consumed or damaged;
5. Whether the SUS tube is blocked, damaged, or worn, and whether there is any deviation from the wire feeding wheel;
6. Wire feeding conduit, lifting method, whether there is deviation from lifting equipment, whether the minimum curvature radius is ensured, and whether the welding wire slides without blockage, wear, or damage;
7. Grounding, cable installation location, whether the installation location of the cable is loose, whether the cable is burned or cracked.
19 Daily maintenance and upkeep of welding machines
1. Check that the output wiring of the welding machine is standardized and firm, and that the direction of the output line is close to vertical downwards, and the angle with the horizontal must be greater than 70 °;
2. Check the fastening of the screws at the cable connection, the screw specification is hexagonal bolt M10 × 30. The flat pad and spring pad are complete and free from rust, oxidation, and other adverse phenomena;
3. Check that the exposed length of the cable at the junction is less than 10mm;
4. Check that the welding machine casing is firmly grounded;
5. Check that the power supply of the welding machine and the grounding of the base material are good and standardized;
6. Check that the cable connections are reliably insulated and wrapped with tape;
7. Check if the screen cover at the connection point of the power cord, welding cable, and welding machine is intact;
8. Whether the cooling fan of the welding machine rotates flexibly and normally;
9. Whether the power switch, power indicator light, and adjustment handle knob are intact, whether the ammeter and voltmeter pointers are flexible and accurate, and whether the surface is clear and free of cracks. The watch cover is intact and can be opened and closed freely.
Daily maintenance and upkeep of 20 sandblasting machines
1. Check if the support rod of the spray gun fixture is loose;
2. Wear condition of the small turntable and fixture;
3. The wear and tear of the spray gun;
4. Wear of sand pipes and air pipes;
5. The wear and tear of the sand return pipe and dust removal pipe;
6. Does the filter cartridge need to be replaced;
7. Does the oil-water filter need to be replaced;
8. Whether the pressure regulating valve and pressure gauge are working properly;
9. The usage of lighting fixtures;
10. The usage of each bearing and swing mechanism;
11. Wear of the upper separator of the machine body;
12. Wear condition of the sand return hopper and sand return pipe at the lower part of the machine body;
13. Is the production of the electrical control box and PLC display clear;
14. Wear and tear of the internal protective layer of the body.

You Might Also Like

Send Inquiry